What is the implementation time for your Cloud DR solution?

The Nuabee solution does not require the deployment of hardware components, and therefore the implementation time of the solution is mainly a function of 2 parameters.

Factors to Consider

The Nuabee solution does not require the deployment of hardware components, and therefore the implementation time of the solution is mainly a function of 2 parameters:

  • The number of servers to protect
  • The ratio between the volume of these servers relative to the available bandwidth and the available time window to perform the backups

Some Examples of Duration

For a scope of 20 servers and a significant available bandwidth (say 500 Mbps) during an 8-hour window at night

  • The initial implementation duration of the DR solution, which ends with the first failover test, is about 4 weeks

For a scope of 100 servers and an average bandwidth (say 300 Mbps) during a 6-hour window at night

  • The initial implementation duration of the DR solution, which ends with the first failover test, will rather be 10/12 weeks

For a scope of 5 servers and a significant available bandwidth (say 500 Mbps) during a 6-hour window at night

  • The initial implementation duration of the DR solution, which ends with the first failover test, can be done in less than 10 days: yes, we have already done it 😉

Factors Increasing the Implementation Duration

We observe cases where project timelines extend, the main reasons are as follows:

  • Limited availability of the client’s technical teams
  • Some clients needing external service providers to deploy backup agents on their applications

Nuabee's contact

65, rue HĂ©non
69004 Lyon - France
Contact Us - Homepage top right - OK